Upcoming Road Projects in the City

Janesville Street from Walworth Avenue to the railroads tracks is currently scheduled for road work starting on
Tuesday, September 6.
The contractor will mill off up to 2 inches of concrete pavement on Tuesday,
September 6, and return on Thursday, September 8, to place asphalt. Painting is scheduled for Friday,
September 9. The contractor is anticipating keeping one lane of traffic open in each direction during the
project.
Motorists can still expect some minor delays due to construction vehicles entering and exiting the work
area. Motorists are urged to use caution in the tight construction zone.

Work will also be occurring on Newcomb Street between E. Milwaukee Street and Clay Street and on Bishop
Street between Newcomb Street and Clay Street.
The contractor will be removing the asphalt on Tuesday,
September 6, and placing asphalt pavement on Thursday September 8. These two streets will be closed to
thru traffic but open for residents residing on those streets.

Share This
Posted in ,

Other Recent Posts

Warhawks Open 2026 with Record-Breaking Day at Perkins Stadium

Fiber Fridays Hosted by the Whitewater Public Library

Film at Seniors in the Park Tuesday, Sept. 8

John’s Disposal Holiday Schedule

This Week’s City & School Board Meetings

Wisconsin Makers to Offer Open Art Workshops

Obituary: Amanda Jean Hunter, 49

Obituary: Ellen Eichmiller, 82

Obituary: Janet Quinn, 71, Jefferson

Whippets Make a Splash at Conference Relays

Whippet Runners Compete at Cam Rock Invite

Our Readers Share: Pandion Haliaetus

Greater Whitewater Committee Set to Host UWW Provost and Vice Chancellor for Academic Affairs

Christine Barwick joins First Citizens State Bank

New Artist’s Work on Display at FCCU