Upcoming Road Projects in the City

Janesville Street from Walworth Avenue to the railroads tracks is currently scheduled for road work starting on
Tuesday, September 6.
The contractor will mill off up to 2 inches of concrete pavement on Tuesday,
September 6, and return on Thursday, September 8, to place asphalt. Painting is scheduled for Friday,
September 9. The contractor is anticipating keeping one lane of traffic open in each direction during the
project.
Motorists can still expect some minor delays due to construction vehicles entering and exiting the work
area. Motorists are urged to use caution in the tight construction zone.

Work will also be occurring on Newcomb Street between E. Milwaukee Street and Clay Street and on Bishop
Street between Newcomb Street and Clay Street.
The contractor will be removing the asphalt on Tuesday,
September 6, and placing asphalt pavement on Thursday September 8. These two streets will be closed to
thru traffic but open for residents residing on those streets.

Share This
Posted in ,

Other Recent Posts

Our Readers Share: Steve Watson – The season is changing and so are the sunrises

WHS Class of 1966 – 60th Reunion

Sign up for Youth Basketball this Week

New Programs Launched to Fight PFAS Statewide & Ensure Access to Clean, Safe Drinking Water

Warhawks Dominate in Homecoming Shutout

Whippets Wrap Up CC Season at WIAA Sectional

Our Readers Share: Randy Cruse – 1982 Brewers Memorabilia

Halloween Film at Seniors In the Park – Tuesday, Oct. 27

This Week’s City & School Board Meetings

Community Survey Highlights Strong Services and Opportunities for Growth

“Hometown Girl” Runs Her First Marathon

Our Readers Share: Ron Binning – Why go all the way to Vermont? / Fall color report link provided

Whippet Soccer Advances in Playoffs After Thrilling Win

Our Readers Share: Tom Ganser – Go Brewers!

#FlashbackFriday with the Historical Society: Minimal football uniforms – 1909