Lakes Drawdown Update

Editor’s note: The following information regarding the work being performed on Cravath and Trippe Lakes was provided by the City of Whitewater.

Work Schedule for week of January 17-21

  • Monday & Tuesday 7am – 7pm
  • Wednesday – Friday morning 24 hours
  • Friday work to finish by 7pm

Prep Week! This week the contractor will be setting the stage for dredging. This includes laying out the wood matting as well as skinning off the snow and vegetation to allow for more frost to set into the lake bed. Our contractor will be working through the night Wednesday and Thursday to remove as much snow and vegetation from the lake bed surface. The colder temperatures through the later part of the week and weekend will allow for frost to work its way down creating a good base to work on. This will reduce the amount of matting needed to perform the project.

Share This
Posted in ,

Other Recent Posts

Our Readers Share: Ed Grosskreutz – Activity around Trippe Lake

Nelson Named to FIRST Wisconsin Youth Advisory Council

WMTV: ‘It’s extremely shocking;’ Whitewater police detail major internet crimes against children investigation

Unity Walk Saturday the 12th at 10 a.m.; Marcha por la unidad

Happy Labor Day

FCCU Announces Promotion of Whitney Townsend to Chief Strategy Officer

Our Readers Share: Ron Binning – Monarch on our zinnia

Boys’ Soccer Continues to Play Strong

Warhawks Open 2026 with Record-Breaking Day at Perkins Stadium

Fiber Fridays Hosted by the Whitewater Public Library

Film at Seniors in the Park Tuesday, Sept. 8

John’s Disposal Holiday Schedule

This Week’s City & School Board Meetings

Wisconsin Makers to Offer Open Art Workshops

Obituary: Amanda Jean Hunter, 49