Hwy 59 is Now Closed from Janesville St. to Rock/Walworth County Line

The “road closed” signs have gone up on Highway 59 and Janesville Street. If you’re looking to get to Kwik Trip on that corner, or one of the several other businesses located in that immediate area, that won’t be a problem. No through traffic is allowed, meaning that anyone driving past that area and the Rock/Walworth County line must be traveling to a home or business in that area or risk being ticketed.

The official detour takes Walworth Avenue/County N all the way to Highway 26. Many residents already take Rock/Walworth County Line Road to Highway 59 on their way to Milton or Janesville. That option is still available. Alternatively, to get to Janesville one may take Highway 89 to Richmond and travel west on County A to Janesville.

As was announced previously on The Banner, this closure is only the first of three phases of this summer’s road construction, as shown below.

The Wisconsin Department of Transportation has announced a roadway improvement project affecting portions of State Highway 59 and State Highway 89 in and near Whitewater.

Construction is expected to begin April 1, 2026, and is anticipated to be completed by the end of June, early July, 2026, weather permitting. The project will occur in three stages.

Stage 1:
Highway 59 from the Rock/Walworth County line to Janesville Street

  • Curb and gutter replacement
  • Sidewalk and pedestrian ramp upgrades
  • Milling existing pavement and installing new asphalt
    Traffic will be detoured using County Highway N and Highway 26.

    Stage 2:
    Highway 59 from Janesville Street to US 12 and Highway 89 from US 12 to Wills Ray Road
  • Milling existing pavement
  • Installing new asphalt
    Traffic will remain open with flagging operations.

    Stage 3:
    Highway 59 from the Rock/Walworth County line to Janesville Street
  • High-friction surface treatment
    Traffic will again be detoured using County Highway N and Highway 26.
    Electronic message boards will be placed one week prior to closures to alert motorists. Please slow down and use extra caution when traveling through construction zones.
    Thank you for your patience during these roadway improvements.

Editor’s note: This press release was provided by Brad Marquardt, city director of public works.

Share This
Posted in

Other Recent Posts

Our Readers Share: Deer at Hillside Cemetery

Nature Lovers Enjoy Swift Night Out

Statement from the City of Whitewater Regarding Wednesday’s Emergency Response at UW-Whitewater

NOTICE: Water System Maintenance – South Side Water Tower

Rock River Community Clinic Becomes Federally Funded FQHC

NOTICE: City to Repave Several Streets

Albert’s Dog Lounge Awarded Grant from Green Bay Packers Foundation

Calling all Food Trucks!

Whitewater Community Foundation Announces New Director

Obituary: Mark Harlan Schmuhl, 71

Public Invited to Join University/Community Band at UWW

UW-Whitewater, Duesterbeck’s Partner to Create Warhawk Beer

A Library Card Hits All the Right Notes: Celebrate Library Card Sign-up Month this September

Former Whippets on UW-Oshkosh Football Roster

First Citizens is Latest Whitewater Business to Volunteer at Habitat Houses